Chevy Chase Village did its own count when Montgomery County released the map of properties covered by ZTA 25-02, its workforce housing zoning amendment. It found ten parcels. Eight face Connecticut Avenue and two face Wisconsin Avenue. One of the Wisconsin parcels is the Saks Fifth Avenue parking lot at 5555 Wisconsin. Once you apply the rules that sit on top of the map, very few of those ten could realistically become a duplex or a small apartment building. A buyer looking at an older house on one of these corridors should treat eligibility as a question to answer one parcel at a time. Inclusion on the map does not make a lot more valuable.
According to Montgomery Planning, the law took effect November 1, 2025. Eleven months later, the county's first official tally of projects built under it is still more than a year away, due December 1, 2027. Until that report arrives, the filters below are the clearest guide to how much the law can change on a given block, and they are easiest to see in Chevy Chase.
What Passed and What Didn't
Much of the confusion goes back to 2024. On June 13 of that year, the Montgomery County Planning Board voted 5-0 to send its Attainable Housing Strategies recommendations to the County Council. That package proposed house-scale duplexes countywide in four residential zones, along with triplexes and quadplexes in certain zones. It did not become law.
The law that did pass was narrower. On July 22, 2025, the Council approved ZTA 25-02 by an 8-3 vote. Councilmembers Andrew Friedson and Natali Fani-González sponsored it. Bethesda Magazine's report on the vote describes the enacted measure as a separate proposal that drew on Attainable Housing Strategies without being based on it. Will Jawando, Sidney Katz and Kristin Mink voted no.
Under ZTA 25-02, the R-40, R-60, R-90 and R-200 zones can have duplexes, triplexes, townhouses and apartment buildings. This applies only where a property's front lot line abuts a Downtown Street or a Boulevard. That road must be master-planned at least 100 feet wide and have three existing travel lanes. By Montgomery Planning's count, the law applies to about 2,429 parcels. About 2,051 of them hold detached houses, which is 1.1% of the county's roughly 184,500 single-family detached parcels.
The Corridors in and Around Chevy Chase
Planning's corridor layer flags qualifying segments with residential frontage on the main roads through Chevy Chase and Bethesda. A few examples:
| Road | Segment flagged | Planned width | Existing lanes |
|---|---|---|---|
| Connecticut Avenue | Western Avenue/DC line to East-West Highway | 120 ft | 6 |
| Wisconsin Avenue | Nottingham Drive to Oliver Street | 120 ft | 6 |
| East-West Highway | Connecticut Avenue to Jones Mill Road/Beach Drive | 120 ft | 4 |
| Bradley Boulevard | Glenbrook Road to Fairfax Road | 120 ft | 6 |
| River Road | Ridgefield Road to Little Falls Parkway | 110 ft | 4 |
| Old Georgetown Road | McKinley Street to 140 ft west of Battery Lane | 130 ft | 4 |
A road name alone does not settle anything. The corridor layer was last updated July 8, 2025, before the Council's final vote. The parcel map carries its own warning that inclusion or exclusion may be imperfect. The real test is a parcel lookup on Montgomery Planning's applicable-properties map, followed by the screens described below.
Running the Village's Ten Through the Filters
The map put ten Chevy Chase Village parcels in scope. Here is how they hold up against the rules that apply after the map:
- One is a parking lot. The Saks Fifth Avenue lot at 5555 Wisconsin Avenue is the only parcel on the list without a single-family home.
- One is a flag lot. The Village has identified 5804 Connecticut Avenue as an existing flag lot. Existing flag lots, through lots, lots without road frontage, and corner lots addressed from the side street cannot use the law.
- Most of Connecticut Avenue is historic. The Village's impact sheet lists five Connecticut Avenue properties as Outstanding resources in the Chevy Chase Village Historic District and two as Contributing. One address on the Outstanding list, 5903, does not appear among the eligible parcels and may be a typo. According to the sheet, Rebeccah Ballo, the Historic Preservation Commission's planning supervisor, said both categories are likely ineligible for substantial elective demolition under Chapter 24A of the County Code.
The Village Board asked the Council to exempt all properties in historic districts. Planning's current FAQ treats those properties differently. Any alteration needs a Historic Area Work Permit, and the HPC reviews construction, additions, grading and tree removal. It may also impose stricter design requirements than the zoning does. So on a historic lot, the zoning permits a triplex, and a separate review process controls whether the house standing there can come down.
After these screens, the Village has one commercial parking lot, 5701 Wisconsin Avenue, and possibly one or two Connecticut Avenue houses outside the historic lists. That is the realistic pool. The Town of Chevy Chase adds its own layer. The Town's land-use guide says county and town rules both govern property there, and most projects need permits from both.
The Math a Builder Runs
Suppose a lot clears every screen. The next question is whether a small multi-unit building outperforms the use these lots already have, which is a large single-family replacement home.
Montgomery Planning studied 683 replacement homes built after 2011. The original houses averaged 1,500 gross square feet and the replacements averaged 3,730. The new homes sold for more than $1.6 million on average, over 2.5 times the value of what they replaced. Planning also noted that these homes are nearly always built on spec. That is a historical sample, not a current price, but it shows that the single-family teardown was already well established when ZTA 25-02 arrived.
Compare the two paths on the same lot:
- Single-family rebuild: under Montgomery County's R-60 development standards, lot coverage is capped at 35% and height at 35 feet to the roof peak. Smaller infill lots get lower coverage caps. This goes through the usual building permit process.
- ZTA 25-02 project: the limits are 1.25 FAR and 40 feet. With three or more units, at least 15% must be workforce housing, which serves households earning up to 120% of area median income, with a minimum of one unit. Applications require public notice, a Development Review Committee meeting, and a Planning Board public hearing and decision.
On a 6,000-square-foot lot, 1.25 FAR works out to 7,500 square feet of floor area. That is about twice the average replacement home in Planning's sample. The extra area comes with a public hearing, and once the project reaches three units, it also comes with a unit priced to an income limit. A duplex avoids the workforce requirement, since that requirement starts at three units. Even so, the hearing applies to the optional method, and a duplex has to beat a single large house that a buyer will pay for in one transaction.
Lot assembly is limited too. SRA 25-02, adopted October 14, 2025, allows no more than three eligible parcels to be combined, with caps by zone. Those caps are 23,400 square feet in R-60 and 33,600 in R-90. The amendment also bars creating new flag lots, through lots, or lots without frontage for this method.
When the County Will Have a Count
The Council wrote the comparison into the law. The final ZTA requires the Planning Board to report every two years. Each report must count rebuilt single-family homes, tracked through building permits, alongside projects built under the workforce housing measure. The first report is due December 1, 2027. Until then, the best public signal is the county's development records. One 2026 River Road plan in those records is River Road Estates, case 120260120. It is a preliminary plan for four detached single-family homes in the R-200 zone at Newhall and Persimmon Tree Roads. It is not a workforce housing application.
For a buyer comparing an older house on Connecticut Avenue with one on a side street, the zoning change usually affects a few details. It matters only after you have checked historic status, lot shape, and frontage for that specific address.
Questions Buyers Ask
Can my neighbor on a side street build a triplex now? Usually not. The front lot line has to abut a qualifying Downtown Street or Boulevard, and lots addressed from a side street at a corner are excluded.
Does the law force anyone to sell or redevelop? No. Planning states that the ZTA only allows owners of applicable parcels to build other housing types if they choose to. It does not authorize eminent domain.
Does parking limit a corridor project? It depends on transit distance. A 2024 change, ZTA 23-10, allows minimum parking to drop to zero within half a mile of a Metro or Purple Line station. ZTA 25-02 did not reduce parking requirements any further.
If you are weighing a corridor-fronting house in Chevy Chase, the eligibility screen comes before any design work. Historic classification, lot shape, frontage, and the Town or Village permit layer decide what the site can hold. At Chesapeake Custom Homes & Development, Adam Goozh reviews those constraints with you at the parcel level before you commit to a purchase or a plan. Schedule a Feasibility Consultation to see what your lot can support.
This article is general information, not legal, tax or financial advice. Consult a qualified professional about your situation.